 Post subject: Ohio Vintage Coal's "new" shop track construction
PostPosted: Tue Jul 17, 2007 3:05 am 
Offline
User avatar

Joined: Mon May 08, 2006 2:16 pm
Posts: 1500
Location: Central Ohio
Well we have been slow posting this up. We broke ground over 3 weeks ago on our new shop track.

With our NEW machine shop/ repair shop it just would not be complete without a track serving it. We had constructed the track with 60 lb rail DUAL GAUGE 36" & 42". We left plenty of room for future expansion for additional gauges.

Special thanks to the construction crew:
Pete J. , Dozer operator, Backhoe operator
Ron J. , track materials
Mike S., track construction & spiker operator
Mike J., track construction & job supervisor

_________________
Pioneering the next INDUSTRIAL REVOLUTION (Preservation ! ). . . Saving equipment (1) mine site at a time.


Top
 Profile  
 
 Post subject:
PostPosted: Tue Jul 17, 2007 5:44 am 
Offline
User avatar

Joined: Fri Jul 15, 2005 2:34 pm
Posts: 6872
Location: Within 60 Miles of the Northern Anthracite Field
blah, too professional :lol: nice job boys! like the automatic spiker, are you using full size spikes?

_________________
Come over to the Dark Side....... We have Cookies!


Top
 Profile  
 
 Post subject:
PostPosted: Tue Jul 17, 2007 8:00 am 
Offline
User avatar

Joined: Mon May 08, 2006 2:16 pm
Posts: 1500
Location: Central Ohio
Almost the same spikes but these are shorter, easier with the automatic machine.

_________________
Pioneering the next INDUSTRIAL REVOLUTION (Preservation ! ). . . Saving equipment (1) mine site at a time.


Top
 Profile  
 
 Post subject:
PostPosted: Wed Jul 18, 2007 6:39 pm 
Offline
User avatar

Joined: Fri Jul 15, 2005 2:34 pm
Posts: 6872
Location: Within 60 Miles of the Northern Anthracite Field
just watched the vid of the automatic spiker.......must be nice :roll:

_________________
Come over to the Dark Side....... We have Cookies!


Top
 Profile  
 
 Post subject:
PostPosted: Wed Jul 18, 2007 7:27 pm 
Offline
User avatar

Joined: Mon May 08, 2006 2:16 pm
Posts: 1500
Location: Central Ohio
We have been building standard gauge track across the midwest & that piece of equipment is a back saver. Easy to transport & runs great off one of our air compressors. We used to operate a huge Hydraulic spiker for standard gauge. It was heavy but it picked the tie up & squeezed the spike into the tie. Two operators sat side by side & had two alignment joysticks but if you missed the tie plate holes it just bent the spike over.

_________________
Pioneering the next INDUSTRIAL REVOLUTION (Preservation ! ). . . Saving equipment (1) mine site at a time.


Last edited by rail haulage miners on Thu Jul 19, 2007 12:00 am, edited 1 time in total.

Top
 Profile  
 
 Post subject:
PostPosted: Wed Jul 18, 2007 10:04 pm 
Offline
User avatar

Joined: Fri Jul 15, 2005 2:34 pm
Posts: 6872
Location: Within 60 Miles of the Northern Anthracite Field
nice, i have an automatic spiker too......... its called adam, banks and mike :lol: anyways ,if we were pounding into standard ties man we would probably do 2 or 3 a night.

_________________
Come over to the Dark Side....... We have Cookies!


Top
 Profile  
 
 Post subject:
PostPosted: Thu Jul 19, 2007 8:02 am 
Offline
User avatar

Joined: Mon May 08, 2006 2:16 pm
Posts: 1500
Location: Central Ohio
Interesting that is enough people to form a track construction UNION. Who will be the union president then?

_________________
Pioneering the next INDUSTRIAL REVOLUTION (Preservation ! ). . . Saving equipment (1) mine site at a time.


Top
 Profile  
 
 Post subject:
PostPosted: Thu Jul 19, 2007 12:07 pm 
Offline
User avatar

Joined: Fri Jul 15, 2005 2:34 pm
Posts: 6872
Location: Within 60 Miles of the Northern Anthracite Field
oh, boy dont start the president discussion again :lol:

_________________
Come over to the Dark Side....... We have Cookies!


Top
 Profile  
 
 Post subject:
PostPosted: Thu Jul 19, 2007 5:08 pm 
Offline
User avatar

Joined: Mon May 08, 2006 2:16 pm
Posts: 1500
Location: Central Ohio
Again, now we got to know about this.

_________________
Pioneering the next INDUSTRIAL REVOLUTION (Preservation ! ). . . Saving equipment (1) mine site at a time.


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 9 posts ] 

All times are UTC - 5 hours [ DST ]


Who is online

Users browsing this forum: No registered users and 30 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group